Product Description

BG778 (DPU-301) is an emergency two-component hydrophobic polyurethane grouting material. After mixed the A and B components, they will react, foam and solidify immediately when they contact with water. They start to foam at 15 seconds and solidify at 60 seconds. The volume expands and forms a foam that is insoluble in water and resistant to chemical corrosion. It has a large penetration radius and solidification volume ratio, and can be poured into 8μm fine cracks. It can not only waterproof and plug leaks, but also has a certain reinforcement effect. It is widely used in subway tunnels, water conservancy and hydro-power, ports, underground garages, sewers, and other waterproof and plug leak reinforcement engineering fields.

Product Detail

BG778 (DPU-301) is an emergency two-component hydrophobic polyurethane grouting material,

which immediately reacts with water,expands in volume and produces an insoluble foaming body

which can not only prevent water leakage, but also has reinforcement effect. Widely used in subway

tunnels, water conservancy and hydropower, underground garage, sewers and other waterproof and 

plugging reinforcement engineering fields.



1.Product characteristics

 Curing fast, rapid reaction with water, foaming, curing, reaction time can be adjusted according to the amount of A components, generally controllable curing in tens of seconds to a few minutes;

 Has good hydrophobic property, chemical stability;

 High strength, when foaming under closed condition, the compressive strength can reach more than 20 MPa within a few hours;

 Has a large permeability radius and solidification volume ratio, chemical reaction occurs rapidly in water, and great expansion pressure will be Produced at the same time, push the slurry to the depths of the crack to form a tough solid.



2. Scope of application

 Water tank, water tower, basement, bomb shelter and other buildings to plug leakage and waterproof and anti-corrosive coating;

 Corrosion protection of metal and concrete pipes and steel structures; llUnderground,tunnel,building,foundation,reinforcement,and,ground,dustprooftreatment

 Leakage plugging and reinforcement of deformation joints, construction joints and structural cracks in construction projects;

 Port, wharf, pier, dam, hydropower station curtain grouting plugging andreinforcement;

 Wall plugging in geological drilling, selective water plugging in oil mining and water stop in mine.


3.Packaging, storage and transport

 Products stored in clean, dry, sealed iron drums, volume of 20 kgs / barrels, 10kgs/ barrels;

 Transport should prevent rain, exposure, extrusion, collision, to ensure that the packaging is intact;

 Products should be stored in a ventilated, dry, cool place to prevent direct sunlight exposure to avoid rain. Storage temperature should not exceed 40℃;

 Under normal storage conditions, the shelf life is 6months.


If necessary, MSDS can be offered upon your requirement

4.Typical performance indicators


Item Test Result
A components B components
Appearance Pale yellow transparent liquid Brown transparent liquid
Density/ g/cm3 1.05-1.0 1.15-1.25
Viscosity/ mpa·s(23±2℃) ≤60 ≤600
Solid content /% - ≥90

5. Reaction time

The reaction time depends not only on the rock temperature, but also on the temperature of the product. If the reaction time under different catalyst dosage is measured under laboratory conditions, it is best to carry out field experiments before grouting


Reaction time of 10% water and different A components at 20℃ temperature
A component dosage 5% 10% 15% 20%
Begin reaction (s) 15 13 10 10
End reaction (S) 90 60 50 50
expansion rate About 30 About 30 About About30